Report Back to Projects
Ongoing Sanitation Project Approved

Construction of Biogas Production Unit at Siakago Girls Secondary School

Embu · Mbeere South · Ruguru/ngandori

Overall Progress
5.00%
Project Overview
Implementing Agency
Tana Water Works Development Agency
Programme
Kenya Towns Sustainable Water Supply and Sanitation Programme
Start Date
-
Planned End
-
Actual End
-
Contractor
Ranju Limited
Consultant
-
Location Type
Rural
Target Areas
Siakago Girls Secondary School
Scope of Works
 Construction of an Anaerobic Reactor  Construction of a horizontal flow constructed wetland Construction of a treated effluent recovery pond
Impacts
Improves access to clean water and create employment opportunities
Key Challenges
Late disbursement of government funds.
Remarks
Need for Improved Coordination and Timely Funding
GPS Coordinates
9935374.000000000,9999999.999999999
Funding Sources

No funding sources recorded.

Total KES 0.0M
Beneficiaries
1
Households
1,000
Population
Created 16 Aug 2026, 15:50