Completed
Borehole
Approved
Kavaci Primary School Borehole
Embu · Mbeere South · Nthawa
Overall Progress
100.00%
Project Overview
Implementing Agency
Tana Water Works Development Agency
Programme
Water for Schools
Start Date
-
Planned End
-
Actual End
-
Contractor
Drilling works contractor- instapump Equipping contractor- Bowquinner
Consultant
-
Location Type
Rural
Target Areas
Kavaci Primary School
Scope of Works
Drilling, development and test pumping
Impacts
Improves access to clean water and create employment opportunities
Key Challenges
Late disbursement of government funds.
Remarks
Awaiting Equipping
GPS Coordinates
-0.568856919,37.664517820
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 1.4M
Total
KES 1.4M
Beneficiaries
1
Households
700
Population
Technical Specs
Storage Reservoir
24.00 m³
Water Kiosks
1