Ongoing
Water Supply Project
Approved
Gitije Kandugu Water Project Phase II-distribution project
Tharaka Nithi · Maara · Muthambi
Overall Progress
43.00%
Project Overview
Implementing Agency
Tana Water Works Development Agency
Programme
Cross-County Programme
Start Date
-
Planned End
-
Actual End
-
Contractor
Marsabit Central Construction Ltd
Consultant
-
Location Type
Rural
Target Areas
Muthambi ward
Scope of Works
•Extension of water supply line
Impacts
The project will support agricultural activities in the region
Key Challenges
• Delay in the GOK counter fund.
Remarks
The project is ongoing as planned
GPS Coordinates
0.218400000, 37.70780000
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 35.0M
Total
KES 35.0M
Beneficiaries
600
Households
3,000
Population
Technical Specs
Volume Abstracted
4,000.00 m³/day
Created 16 Aug 2026, 15:50