Report Back to Projects
Ongoing Water Supply Project Approved

Ruguta Kathituni- Marigwe Kamachembe Water Project

Tharaka Nithi · Maara · Mitheru

Overall Progress
34.00%
Project Overview
Implementing Agency
Tana Water Works Development Agency
Programme
Cross-County Programme
Start Date
06 Feb 2022
Planned End
-
Actual End
-
Contractor
visrom limited
Consultant
-
Location Type
Rural
Target Areas
Mitheru ward
Scope of Works
● Construction of 2 No. 225m3 tanks ● Laying of pipeline 15210m-225mm,160mm, 90mm Dia. Construction of 1No 150m3 tank
Impacts
The project will support agricultural activities in the region
Key Challenges
• Delay in the GOK counter fund.
Remarks
The project is ongoing as planned
GPS Coordinates
29725, 37.67027
Funding Sources
Gok
🇰🇪 Domestic · Grant
KES 63.8M
Total KES 63.8M
Beneficiaries
260
Households
1,300
Population
Technical Specs
Volume Abstracted 4,000.00 m³/day
Created 16 Aug 2026, 15:50
County Overview
Loading…
Loading…

Fetching entity performance details…