Completed
River Intake
Approved
Liter-Cheptulel Water Supply Project
West pokot · Pokot Central · Lomut
Overall Progress
100.00%
Project Overview
Implementing Agency
North Rift Valley Water Works Developmnet Agency
Programme
North Rift Valley WWDA Projects
Start Date
-
Planned End
-
Actual End
-
Contractor
Hampton Construction Limited
Consultant
-
Location Type
Rural
Target Areas
Cheptulel TTI
Cheptulel Boys Secondary
Kokwombeses Secondary
Cheptulel Girls Secondary
Cheptule Primary
Arpollo Primary
Sapulmoi Primary
Chemaley Primary
Kosilot Primary
Cheptulel Shoppping Centre
Administrative areas
Scope of Works
1. Intake works;
2. Gravity Main Pipeline – 2.50 Km
a) 4" dia Galvanized Iron Class B Section – 1.00 Km
b) HDPE Diameter 110 mm – 1.50 Km
3. Distribution Pipelines
a) Ksaa -TTI Tank Pipeline (1 Km long 3" GI Pipe)
b) TTI line (0.8 Km long Diameter 63 mm)
c) Cheptulel Primary Line (2.2 Km long Diameter 75 mm)
4. Rehabilitation of existing 3 No. Masonry Tanks
5. Construct a 2 m3 Break Pressure Tank
6. Other Civil Works
Impacts
Improved security status across the two communities
Improved access to water
Cheptulel is now more habitable as evidenced by improved settlement increasing land productivity and enhanced livelihoods
Re-opening of closed schools
Key Challenges
Insecurity within the project area
Difficult terrain
Remarks
The project is complete and operational
Request for additional funds to implement phase II of the project
GPS Coordinates
latitudes 1.287° to 1.303°
longitudes
35.59° to 35.62°
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 30.0M
Total
KES 30.0M
Beneficiaries
3,000
Households
15,000
Population
Technical Specs
Volume Abstracted
1,500.00 m³/day
Storage Reservoir
100.00 m³
Treated Water Mains
3.50 km
Distribution Lines
3.00 km
Connections
50
Non-Sewered Sanitation Facilities
2
Created 16 Aug 2026, 15:51