Completed
Springs: Extension of pipeline
Approved
Eliye Kaolokol
Turkana · Turkana Central · Kangatotha/ Kalokol
Overall Progress
100.00%
Project Overview
Implementing Agency
North Rift Valley Water Works Developmnet Agency
Programme
North Rift Valley WWDA Projects
Start Date
04 Oct 2024
Planned End
08 Oct 2024
Actual End
09 Mar 2024
Contractor
Rhumas Co. Ltd
Consultant
-
Location Type
Rural
Target Areas
Eliye, Wadach, Lobolo, Loyolo,.. & Kalokol
Scope of Works
Rehabilitation of intake and laying of 10km water distribution main line
Impacts
Residents accessing better quality water (Non-saline) closer to settlements
Key Challenges
High demand versus low supply, vulnerable infrastructure
Remarks
Phase 1 of the project is complete and operational. Phase 2 undertaken by CRVWWDA for completion of pipeline to Kalokol, 80% complete
GPS Coordinates
3.14'58.32"N 36.01'06.37"E
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 20.0M
Total
KES 20.0M
Beneficiaries
2,000
Households
10,000
Population
Technical Specs
Volume Abstracted
100.00 m³/day
Storage Reservoir
150.00 m³
Treated Water Mains
40.00 km
Distribution Lines
15.00 km
Water Kiosks
10
Connections
100