Ongoing
Spring
Approved
Kamasat Water Project
Elgeyo-Marakwet · Marakwet West · Lelan
Overall Progress
60.00%
Project Overview
Implementing Agency
North Rift Valley Water Works Developmnet Agency
Programme
North Rift Valley WWDA Projects
Start Date
05 Aug 2024
Planned End
03 Aug 2025
Actual End
-
Contractor
Chestev Construction Co.
Consultant
-
Location Type
Rural
Target Areas
Kamasat village, Kamasat Primary School, Spectrum academy
Scope of Works
Spring development and protection, installation of pumping system complete with 10 KM transmission and distrbution lines.
Impacts
Increased water coverage
Improved Quality of Life
Reduction in Waterborne Diseases
Better Hygiene and Sanitation
Increased Productivity
Community Cohesion
Reforestation and Soil Conservation
Key Challenges
Issues between the project host community and the immediate neighbouring community on the source of water and extent of coverage
Remarks
Community issues resolved and the project progressing well
GPS Coordinates
latitudes 1.°00'33.7" N
longitudes
35° 27'30.73"
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 20.0M
Total
KES 20.0M
Beneficiaries
215
Households
1,075
Population
Technical Specs
Volume Abstracted
250.00 m³/day
Storage Reservoir
170.00 m³
Treated Water Mains
2.00 km
Distribution Lines
8.00 km
Water Kiosks
4
Connections
20
Created 16 Aug 2026, 15:51