Report Back to Projects
Proposed Nil Approved

Losito Kapngetuny

Uasin Gishu · Ainabkoi · Ainabkoi/Olare

Overall Progress
0.00%
Project Overview
Implementing Agency
North Rift Valley Water Works Developmnet Agency
Programme
North Rift Valley WWDA Projects
Start Date
-
Planned End
-
Actual End
-
Contractor
Kenoru Investment
Consultant
-
Location Type
-
Target Areas
Kapngetuny, Losoito
Scope of Works
Rehabilitation of the treatment plant, solarization, construction of 100m3 tank, 1.5km pipleine extension.
Impacts
Over 100 households connected
Key Challenges
Accessibility to intake works
Remarks
Substantially Complete and operational.
GPS Coordinates
NIL
Funding Sources
Gok
🇰🇪 Domestic · Grant
KES 15.0M
Total KES 15.0M
Beneficiaries
400
Households
0
Population
Created 16 Aug 2026, 15:51