Ongoing Water Supply Approved

Construction of Masalani- Gababa Pipeline Extension and Axillary Works

Garissa · Ijara · Masalani

Overall Progress
56.77%
Project Overview
Implementing Agency
Northern Water Works Development Agency
Programme
Ijara Water Supply Project
Start Date
-
Planned End
-
Actual End
-
Contractor
Za construction and Transporters limited
Consultant
-
Location Type
-
Target Areas
Gababa, Ijara TveT
Scope of Works
Laying and backfilling of 17km DN 160-110 PN12.5 pipeline and civil works associated, Construction of 1 No 150m3 Elevated steel tank, Rehabilitation of 2 No 150m3 Elevated steel tank and 1 no, improvement of Masalani water facilities.
GPS Coordinates
624923.35 m E, 10187681.47 m N.
Funding Sources

No funding sources recorded.

Total KES 0.0M
Beneficiaries
6,600
Households
6,600
Population
Technical Specs
Volume Abstracted 2,200.00 m³/day
Treatment Capacity 2,000.00 m³/day
Storage Reservoir 150.00 m³
Treated Water Mains 17.00 km