Completed
Water Pan
Approved
Lodungokwe II Water Pan
Samburu · Samburu East · Wamba
Overall Progress
100.00%
Project Overview
Implementing Agency
Northern Water Works Development Agency
Programme
Northern WWDA Projects
Start Date
-
Planned End
-
Actual End
09 Jan 2025
Contractor
Abdi Mon Enterprise Limited
Consultant
-
Location Type
-
Target Areas
NIL
Scope of Works
Construction of 1 no. water pan, Construction of spillway, Auxiliary works
Impacts
To Increase water storage to be used in dry periods to reduce the cost of living and inclusive growth
Key Challenges
Insufficient budgetary allocations
Remarks
NIL
GPS Coordinates
279372 m E,
95796 m N
Funding Sources
No funding sources recorded.
Total
KES 0.0M
Beneficiaries
300
Households
1,800
Population
Created 16 Aug 2026, 15:51