Completed
Water Pan
Approved
Construction of Ereja Godana Pan
Mandera · Mandera South · Kutulo
Overall Progress
100.00%
Project Overview
Implementing Agency
Northern Water Works Development Agency
Programme
Northern WWDA Projects
Start Date
01 Apr 2024
Planned End
-
Actual End
12 Jan 2025
Contractor
Yatho Company Limited
Consultant
-
Location Type
-
Target Areas
NIL
Scope of Works
Construction of 1 no. water pan, Construction of spillway, Auxiliary works
Impacts
To Increase water storage to be used in dry periods to reduce the cost of living and inclusive growth
Key Challenges
Insufficient budgetary allocations
Remarks
NIL
Funding Sources
No funding sources recorded.
Total
KES 0.0M
Beneficiaries
200
Households
1,200
Population
Technical Specs
Storage Reservoir
30,000.00 m³