Report Back to Projects
Completed Water Pan Approved

Sarai/Mbagas Water Pan

Marsabit · Laisamis · Korr/Gurunit

Overall Progress
100.00%
Project Overview
Implementing Agency
Northern Water Works Development Agency
Programme
Northern WWDA Projects
Start Date
02 Aug 2024
Planned End
02 Apr 2025
Actual End
10 Jan 2028
Contractor
Trippleage Investment Limited
Consultant
-
Location Type
-
Target Areas
NIL
Scope of Works
Construction of 1 no. water pan, Construction of spillway, Auxiliary works
Impacts
To Increase water storage to be used in dry periods to reduce the cost of living and inclusive growth
Key Challenges
Insufficient budgetary allocations
Remarks
NIL
GPS Coordinates
325410 m E, 178036 m N
Funding Sources

No funding sources recorded.

Total KES 0.0M
Beneficiaries
200
Households
1,200
Population
Technical Specs
Storage Reservoir 25,000.00 m³
Created 16 Aug 2026, 15:51
County Overview
Loading…
Loading…

Fetching entity performance details…