Ongoing
Borehole
Approved
Namayana Karate Borehole
Marsabit · Saku · Karare
Overall Progress
10.00%
Project Overview
Implementing Agency
Northern Water Works Development Agency
Programme
Construction of Water Pans and Small Dams:
Start Date
01 Jan 2024
Planned End
-
Actual End
-
Contractor
Al Hussain Investment Limited
Consultant
-
Location Type
-
Scope of Works
Drilling, development and test pumping
Impacts
To Increase water storage to be used in dry periods to reduce the cost of living and inclusive growth
Key Challenges
Insufficient budgetary allocations
GPS Coordinates
377673.67 m E,
243533.33 m N
Funding Sources
No funding sources recorded.
Total
KES 0.0M
Beneficiaries
200
Households
1,200
Population
Created 16 Aug 2026, 15:51