Ongoing
Water Pan
Approved
Rehabilitation of Alungu Dam
Mandera · Lafey · Alungu
Overall Progress
1.00%
Project Overview
Implementing Agency
Northern Water Works Development Agency
Programme
Northern WWDA Projects
Start Date
-
Planned End
-
Actual End
-
Contractor
Kimzam Energy Limited
Consultant
-
Location Type
-
Target Areas
NIL
Scope of Works
Construction of 1 no. water pan, Construction of spillway, Auxiliary works
Impacts
To Increase water storage to be used in dry periods to reduce the cost of living and inclusive growth
Key Challenges
Insufficient budgetary allocations
Remarks
NIL
Funding Sources
No funding sources recorded.
Total
KES 0.0M
Beneficiaries
200
Households
1,200
Population
Created 16 Aug 2026, 15:51