Report Back to Projects
Ongoing Borehole

Londopua Borehole

Mombasa · Likoni · Bofu

Overall Progress
40.00%
Project Overview
Implementing Agency
Central Rift Valley Water Works Development Agency
Programme
Equalization Fund Project Phase ll
Contractor
Darglobe Company Limited
Consultant
Start Date
03 Jul 2024
Planned End
03 Oct 2024
Actual End
Scope of Works
Drilling, Equipping and Civil Works with elevated tower
Impacts
Improve access to water
Key Challenges
Borehole dry
Funding Sources

No funding sources recorded.

Total KES 0.0M
Beneficiaries
1,200
Households
6,000
Population