Ongoing
Sewer construction
Approved
Lot 5 - Construction of Dagoreti sewers
Nairobi · Dagoretti North · gatina ward, kileleshwa ward
Overall Progress
98.20%
Project Overview
Implementing Agency
Athi Water Works Development Agency
Programme
Nairobi City Regeneration programme
Start Date
-
Planned End
-
Actual End
-
Contractor
Octagon builders and General suppliers limited
Consultant
Engplan consulting engineers limited consulting servicees
Location Type
Urban
Target Areas
Braeside, Muthangari, Mageta, Gatina Congo and Salim roads
Scope of Works
Construction of 4.1km of DN 300mm spigot and socket precast concrete pipe sewer lines to extend Braeside, Muthangari and Mageta sewer lines, Construction of precast manholes and bavkdrops of nominal bore 1050mm, Construction of sewer road crossings works, sewer and manhole unblocking, desilting and cleaning, Construction of 2km of DN 300mm spigot and socket precast concrete pipes sewer line s to extend Gatina, Congo and Salim road sewer lines
Impacts
Improved sanitation in Dagoretti area and its environs
Key Challenges
working under stringent COVID 19 rules and regulations
GPS Coordinates
-1.2750, 36.7200
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 66.7M
Total
KES 66.7M
Technical Specs
Reticulation Sewer
6.10 km