Report Back to Projects
Ongoing Water supply, borehole, Treatment plant Approved

LOT 2: KISERIAN – ONGATA RONGAI WATER SUPPLY SYSTEM

Kajiado · Kajiado North · Ongata Rongai, Nkaimurunya,Oloolua, Olkeri, Ngong

Overall Progress
97.00%
Project Overview
Implementing Agency
Athi Water Works Development Agency
Programme
Nairobi Satellite Towns Water and Sanitation Development Programme (NST-WSDP), Phase 1
Start Date
-
Planned End
11 Jan 2024
Actual End
-
Contractor
China Jiangxi International Economic & Technical Cooperation Co Ltd
Consultant
Posch & Partners, Austria, with Norken International, Kenya
Location Type
Urban
Target Areas
Ongata Rongai, kiserian, Mbagathi, Karen
Scope of Works
Water treatment,building a transmission main, Construction of storage tanks at Kiserian Schopol Tank, 800 m³, Narumoru Tank, 100 m³, Gataka Tank, 2,300 m³, Water distribution by Constructing 210 km of ring mains and distribution network in Kiserian and Ongata Rongai (OD63 to DN500):, Builiding new main office building for OWSC at Mbagathi tank site, Rehabilitation of 6 existing boreholes, 10 new boreholes, with local supply systems
Impacts
Increased water supply to serve an additional 46,000 people in Ongata Rongai, Kiserian, Mbagathi and Karen. Economic Growth. Improved Public Health
Key Challenges
Insufficient water for the project area:dissatisfied consumers hence rationing will be soon needed if there are no additional sources. New KPLC connections are needed at various boreholes.
Remarks
The following parts of the Works were all taken over: Mbagathi WTP, Kiserian Office, Borehole, Rising Main, Kiserian School Tank and DMAs K1 and K2, Mbagathi Head Office for OWSC, including site works and buildings. Independent Boreholes taken over are Enkasurai, Kisaju, Keekonyonke, Olkudate and Olmeroi.
GPS Coordinates
-1.397683, 36.736749
Funding Sources
Gok
🇰🇪 Domestic · Grant
KES 110.6M
Kfw
🌍 Foreign · Loan
KES 995.7M
Total KES 1,106.4M
Beneficiaries
9,200
Households
46,000
Population
Technical Specs
Volume Abstracted 6,900.00 m³/day
Treatment Capacity 15,700.00 m³/day
Storage Reservoir 3,343.00 m³
Treated Water Mains 13.10 km
Distribution Lines 210.00 km
Connections 5,727