Ongoing
Borehole, Water Supply
Approved
Nairobi Arboretum
Nairobi · Dagoretti North · Kilimani
Overall Progress
1.00%
Project Overview
Implementing Agency
Athi Water Works Development Agency
Programme
Drilling & Equipping of 8No. Boreholes and Construction of 4No. Elevated Water Tanks with Associated Water Distribution Networks. Lot 5
Start Date
06 May 2020
Planned End
02 Mar 2021
Actual End
02 Mar 2021
Contractor
Export Hydro Pump and Services Limited
Consultant
-
Location Type
Urban
Target Areas
Kilimani
Scope of Works
Drilling and equipping of borehole,Borehole chamber and pump house,Water kiosk and Reticulation
GPS Coordinates
1.2785277,36.7985582
Funding Sources
No funding sources recorded.
Total
KES 0.0M
Created 16 Aug 2026, 15:51