Ongoing
Borehole, Water Supply
Approved
Ndurarua Primary School
Nairobi · Dagoretti North · Kabiro
Overall Progress
1.00%
Project Overview
Implementing Agency
Athi Water Works Development Agency
Programme
Drilling & Equipping of 2No. Boreholes and Construction of 6No. Elevated Water Tanks with Associated Water Distribution Networks. Lot 6
Start Date
-
Planned End
-
Actual End
-
Contractor
Turn-O- Metal Engineers Ltd
Consultant
-
Location Type
Urban
Target Areas
Kabiro
Scope of Works
Drilling and equipping of borehole,Borehole chamber and pump house,Power Connection, 3No. Water Kiosk & Associated Piping and 1No. Elevated Tank
GPS Coordinates
1.288977,36.7376415
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 9.9M
Total
KES 9.9M
Beneficiaries
13,317
Households
36,228
Population
Technical Specs
Volume Abstracted
300.00 m³/day
Storage Reservoir
24.00 m³
Water Kiosks
3
Created 16 Aug 2026, 15:51