Ongoing
Water Supply
Approved
Bangladesh- Rongai
Kajiado · Kajiado North · Nkaimurunya
Overall Progress
1.00%
Project Overview
Implementing Agency
Athi Water Works Development Agency
Programme
Construction of 8No. Elevated Steel Water Tanks in AWWDA Area. Lot 8
Start Date
-
Planned End
-
Actual End
-
Contractor
David Engineering Limited
Consultant
-
Location Type
Urban
Target Areas
Nkaimurunya
Scope of Works
Supply, delivery and installation of 18m Steel towers and 24m3 pressed steel tank
GPS Coordinates
1.396122,36.7388347
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 1.1M
Total
KES 1.1M
Beneficiaries
560
Households
2,800
Population
Technical Specs
Storage Reservoir
24.00 m³
Created 16 Aug 2026, 15:51
· Last updated 16 Aug 2026, 17:19