Ongoing
Water Supply
Approved
Dandora Ward Admin 1
Nairobi · Embakasi North · Dandora Area I
Overall Progress
1.00%
Project Overview
Implementing Agency
Athi Water Works Development Agency
Programme
Construction of 8No. Elevated Steel Water Tanks in AWWDA Area. Lot 8
Start Date
-
Planned End
-
Actual End
-
Contractor
David Engineering Limited
Consultant
-
Location Type
Urban
Target Areas
Dandora Area I
Scope of Works
Supply, delivery and installation of 18m Steel towers and 24m3 pressed steel tank
GPS Coordinates
1.2551064,36.8891078
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 10.0M
Total
KES 10.0M
Beneficiaries
4,882
Households
24,409
Population
Technical Specs
Storage Reservoir
24.00 m³
Created 16 Aug 2026, 15:51
· Last updated 16 Aug 2026, 17:19