Report Back to Projects
Ongoing Borehole Approved

Nyaberi Primary School Borehole Water Project

Kericho · Soin · Soin

Overall Progress
85.00%
Project Overview
Implementing Agency
Lake Victoria North Water Works Development Agency
Programme
Water Harvesting Programme
Start Date
-
Planned End
-
Actual End
-
Contractor
Dorshaq limited
Consultant
-
Location Type
Rural
Target Areas
Kaitui
Scope of Works
Drilling, Construction of Storage tank, Electromechanical and Civil Works
Impacts
Reduction in waterborne diseases due to access to clean water and improved sanitation, leading to better overall health and reduced healthcare costs. Increased school attendance especially for girls as they spend less time collecting water and managing sanitation needs. Access to clean water and sanitation will increase productivity in the workforce, leading to improved livelihoods and economic growth, women and girls often bear the burden of collecting water, so improved water access will empower them and provide more time for other activities
GPS Coordinates
Latitude -0.2573346 Longitude 35.14512319
Funding Sources

No funding sources recorded.

Total KES 0.0M
Beneficiaries
0
Households
1,000
Population
Technical Specs
Volume Abstracted 20.00 m³/day
Treatment Capacity 20.00 m³/day
Storage Reservoir 50.00 m³
Treated Water Mains 0.20 km
Distribution Lines 0.40 km
Water Kiosks 4
Created 16 Aug 2026, 15:51