Report Back to Projects
Completed Borehole Approved

Equipping of Unii Borehole Water Supply Project

Kitui · Kitui South · Ikanga/Kyatune

Overall Progress
100.00%
Project Overview
Implementing Agency
Tanathi Water Works Development Agency
Programme
Drilling and Equipping of Boreholes
Start Date
03 Dec 2022
Planned End
06 Oct 2022
Actual End
09 Aug 2022
Contractor
Lyjos Enterprises Limited
Consultant
-
Location Type
Rural
Target Areas
Community Schools
Scope of Works
• Installation of submersible pump, • solar installation with steel mounting structure, • Distribution pipeline • 2No water kiosks,
Impacts
The project serves the target area with clean, safe, and affordable water
Key Challenges
The project was delayed due to delayed exchequer release
Remarks
The project is complete, operational, and has been handed over to the community
GPS Coordinates
38.36587, -1.94973
Funding Sources

No funding sources recorded.

Total KES 0.0M
Beneficiaries
264
Households
1,320
Population
Technical Specs
Volume Abstracted 54.00 m³/day
Treatment Capacity 54.00 m³/day
Storage Reservoir 20.00 m³
Treated Water Mains 0.50 km
Distribution Lines 0.70 km
Water Kiosks 2
Connections 5