Completed Water Pan Approved

Chemurtoi Water Pan

Baringo · Tiaty · Sacho

Overall Progress
100.00%
Project Overview
Implementing Agency
Central Rift Valley Water Works Development Agency
Programme
GOK Funded Projects
Start Date
11 Jul 2023
Planned End
02 Jul 2024
Actual End
02 Jul 2024
Contractor
-
Consultant
-
Location Type
Rural
Target Areas
Chemurtoi and adjoining areas
Scope of Works
Construction of 10,560m3 pan
Impacts
Improve access to water
Key Challenges
No challenges
Remarks
Currently in use
GPS Coordinates
0.180601, 35.993567
Funding Sources
Gok
🇰🇪 Domestic · Grant
KES 4.9M
Total KES 4.9M
Beneficiaries
800
Households
4,000
Population
Technical Specs
Storage Reservoir 10,560.00 m³