Completed
Dam
Approved
Kivulini Water Project
Nakuru · Molo · Molo
Overall Progress
100.00%
Project Overview
Implementing Agency
Central Rift Valley Water Works Development Agency
Programme
GOK Funded Projects
Start Date
-
Planned End
-
Actual End
02 Oct 2025
Contractor
-
Consultant
-
Location Type
Rural
Target Areas
Kivulini and adjoining areas
Scope of Works
Construction of Kivulini Small Dam
Impacts
Improved access to water
Key Challenges
No challenges
Remarks
Project is 90% Complete
GPS Coordinates
-0.249527, 35.730781
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 15.2M
Total
KES 15.2M
Beneficiaries
1,000
Households
5,000
Population
Technical Specs
Storage Reservoir
20,000.00 m³