Report Back to Projects
Ongoing Borehole Approved

Nakuru Provincial hospital Borehole

Nakuru · Nakuru West · London

Overall Progress
80.00%
Project Overview
Implementing Agency
Central Rift Valley Water Works Development Agency
Programme
Universal Health Coverage Program
Start Date
-
Planned End
07 Apr 2022
Actual End
07 Apr 2023
Contractor
Kiburu Enterprises Limited
Consultant
-
Location Type
Urban
Target Areas
Nakuru Provincial
Scope of Works
Drilling and capping
Impacts
Improve water access in Nakuru Provincial hospital
Key Challenges
No Challemges
Remarks
Awaiting disbursement of funds for equipping
GPS Coordinates
-0.2780219,36.069856
Funding Sources
Gok
🇰🇪 Domestic · Grant
KES 3.1M
Total KES 3.1M
Beneficiaries
600
Households
3,000
Population
Created 16 Aug 2026, 17:18