Completed
Sewer system
Approved
Kiti Sewerage Project
Nakuru · Bahati · Kiamaina
Overall Progress
100.00%
Project Overview
Implementing Agency
Central Rift Valley Water Works Development Agency
Programme
GOK Funded Projects
Start Date
-
Planned End
-
Actual End
04 Jan 2024
Contractor
-
Consultant
-
Location Type
Rural Urban
Target Areas
Nakuru Kiti region
Scope of Works
Construction of 2.7km of dwc sewer pipeline 225mm diameter
Impacts
Improved sanitation in Nakuru Kiti region
Key Challenges
Reported vandalism
Remarks
complete, awaiting Inspection, commissioning and handover
GPS Coordinates
-0.269526, 36.105003
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 18.6M
Total
KES 18.6M
Beneficiaries
600
Households
3,000
Population
Technical Specs
Trunk Sewer Main
2.70 km