Ongoing
Water Supply
Approved
Construction of Kaptumo water project phase 4 (Kaptumo-Sogon Water Supply)
Baringo · Baringo Central · Kaptumo
Overall Progress
80.00%
Project Overview
Implementing Agency
Central Rift Valley Water Works Development Agency
Programme
GOK Funded Projects
Start Date
02 Oct 2023
Planned End
02 Apr 2024
Actual End
02 Apr 2024
Contractor
-
Consultant
-
Location Type
Rural Urban
Target Areas
Chepkabomo, Sogon,Sogon and Kaptumo Primary and Talai Primary School community
Scope of Works
1. Extension of pipeline from Chepkabomo Masonry sump to Sogon Tank
2. Construction of 1No Water Kiosk
3. Construction of Student Water point
4. Solarization of Kasau Reservoir pumping system
5. Solarization of Talai Borehole
6. Construction of Pit Latrines for Sogon and Kaptumo Primary Schools
7. Construction of Wash basins for Sogon and Talai Primary Schools
8. Construction of 4m high steel tower with 10,000 lts plastic tank for
Talai Primary School and Sogon Dispensary.
Impacts
Improved access to water supply
Key Challenges
Slow contractor mobilization
Remarks
Awaiting contractor to re mobilize
GPS Coordinates
0.574383, 35.800352
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 17.4M
Total
KES 17.4M
Beneficiaries
400
Households
2,000
Population
Technical Specs
Storage Reservoir
40,000.00 m³
Distribution Lines
20.00 km
Water Kiosks
1
Non-Sewered Sanitation Facilities
2
Created 16 Aug 2026, 17:18