Completed
Borehole
Approved
Gichigirira community borehole
Nyandarua · Ndemi · Wanjohi
Overall Progress
100.00%
Project Overview
Implementing Agency
Central Rift Valley Water Works Development Agency
Programme
GOK Funded Projects
Start Date
02 Oct 2024
Planned End
02 Nov 2024
Actual End
-
Contractor
Execel Micro-Invest Limited
Consultant
-
Location Type
Rural
Target Areas
Gichigirira Community and its environs
Scope of Works
Drilling and capping
Impacts
Improved access to water
Key Challenges
1
Remarks
100% Complete
GPS Coordinates
-0.2697854253800908, 36.42008582553257
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 3.0M
Total
KES 3.0M
Beneficiaries
580
Households
2,900
Population
Created 16 Aug 2026, 17:18