Ongoing
Water Supply
Approved
Baraka-Chaka/Tagwa Water Supply Project
Nyeri · Kieni · Ruringu
Overall Progress
80.00%
Project Overview
Implementing Agency
Tana Water Works Development Agency
Programme
Cross- County Bulk Water & Sanitation Program
Start Date
06 Jul 2023
Planned End
06 Jun 2025
Actual End
-
Contractor
Octagon
Consultant
-
Location Type
Rural
Target Areas
Chaka Town and envrons
Scope of Works
· Supply and installation of surface pump, motor and electrical power connection · Laying of rising main Construction of 500m3 ground high tensile steel water tank
Impacts
Improve access to clean water
Key Challenges
Slow progress by the contractor citing financial constraints
Remarks
Improvement acees to clean water
GPS Coordinates
0.500000000,37.333330000
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 63.5M
Total
KES 63.5M
Beneficiaries
3,000
Households
15,000
Population
Technical Specs
Storage Reservoir
500.00 m³