Completed Water Supply Approved

Nkubiu Water Project

Meru · Tigania West · Nkomo

Overall Progress
100.00%
Project Overview
Implementing Agency
Tana Water Works Development Agency
Programme
Cross- County Bulk Water & Sanitation Program
Start Date
09 Nov 2020
Planned End
08 May 2021
Actual End
08 May 2021
Contractor
Shaljo Enterprises Limited.
Consultant
-
Location Type
Rural
Target Areas
Nkomo
Scope of Works
 Laying of 2No. 2.58km parallel lines225 mm and 110 mm
Impacts
Provision of reliable water for domestic and agricultural use.
Key Challenges
GOK late disbursments
Remarks
Complete
GPS Coordinates
0.19765,37.79039
Funding Sources
Gok
🇰🇪 Domestic · Grant
KES 8.5M
Total KES 8.5M
Beneficiaries
500
Households
2,500
Population
Technical Specs
Volume Abstracted 4,000.00 m³/day
Distribution Lines 5.60 km
Connections 500