Report Back to Projects
Ongoing Earthdam Approved

Ura 4 Phase II Earth Dam

Meru · Igembe Central · Kangeta

Overall Progress
35.00%
Project Overview
Implementing Agency
Tana Water Works Development Agency
Programme
Water Harvesting Program
Start Date
-
Planned End
-
Actual End
-
Contractor
Ranju Limited
Consultant
-
Location Type
Rural
Target Areas
Kangeta Community
Scope of Works
Construction of concrete lining on the reservoir
Impacts
Creation of employment to the local populatin and provision of relible water
Key Challenges
Duet to geotechnical site challenges, mutual termination of Contract on-going to enable works re-tendering
Remarks
35% Duet to geotechnical site challenges, mutual termination of Contract on-going to enable works re-tendering
GPS Coordinates
0.221111110,37.894722220
Funding Sources
Gok
🇰🇪 Domestic · Grant
KES 28.4M
Total KES 28.4M
Beneficiaries
200
Households
1,000
Population