Ongoing
Borehole
Approved
Maritati Police Post Borehole
Meru · Buuri · Timau
Overall Progress
35.00%
Project Overview
Implementing Agency
Tana Water Works Development Agency
Programme
Cross- County Bulk Water & Sanitation Program
Start Date
06 May 2024
Planned End
-
Actual End
-
Contractor
Finscope Investment
Consultant
-
Location Type
Rural
Target Areas
Maritati police post maritati vilaage Maritati dispensary and Maritati market
Scope of Works
Drilling, development and test pumping
Borehole drilled to 147.9m and 40m3/h yield obtained
Equipping with solar powered associated works
Last mile connectivity
Impacts
The project will benefit the people of Maritati, Maritati Police, Maritati dispensary and Maritati Market
Key Challenges
Slow progress due to Financial constrains from the contractor
Remarks
Tthre is need for coordination and follow up on contractor's program of work for the project to be completed on time.
GPS Coordinates
0.1113,37.3934
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 19.8M
Total
KES 19.8M
Beneficiaries
300
Households
1,500
Population
Technical Specs
Volume Abstracted
320.00 m³/day
Storage Reservoir
24.00 m³
Distribution Lines
7.20 km
Water Kiosks
1
Connections
800
Created 16 Aug 2026, 17:18