Ongoing
Borehole
Approved
Muthutira Community Borehole
Meru · Tigania West · Mbeu
Overall Progress
50.00%
Project Overview
Implementing Agency
Tana Water Works Development Agency
Programme
Cross- County Bulk Water & Sanitation Program
Start Date
-
Planned End
-
Actual End
-
Contractor
Octagon Bulders Limited
Consultant
-
Location Type
Rural
Target Areas
Muthutira Community
Scope of Works
Drilling, development and test pumping
Drilled to 156m depth and 29m3/h yield established
Impacts
Provision of safe water when complete
Key Challenges
GOK late disbursments
Remarks
Drilling complete, awaiting equipping and last mile connectivity
GPS Coordinates
8091.000000000,364158.000000000
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 1.9M
Total
KES 1.9M
Beneficiaries
200
Households
1,000
Population
Technical Specs
Volume Abstracted
212.00 m³/day
Storage Reservoir
24.00 m³
Created 16 Aug 2026, 17:18