Ongoing
Water Supply Project
Approved
Timau Water Project
Meru · Buuri · Kisima
Overall Progress
0.00%
Project Overview
Implementing Agency
Tana Water Works Development Agency
Programme
National Urban Water Supply and Sanitataion Program (NUWSSP) Ph II
Start Date
-
Planned End
-
Actual End
-
Contractor
-
Consultant
-
Location Type
Urban
Target Areas
Timau town and its environs.
Scope of Works
▪ - Construction of water intake on Timau River springs.
• Laying of 9km DN
400mm raw water main
• Construction of 10,000m3/day conventional water treatment plant
• Laying of 3Km
DN200mm, DN 160mm and DN110 treated water mains
• Laying of 20km reticulation network comprising of pipes ranging from DN 110m- 63mm diameter
Impacts
Provision of reliable water for domestic and agricultural use.
Key Challenges
Awaiting Funds allocation
Remarks
Project designed
Funding Sources
No funding sources recorded.
Total
KES 0.0M
Beneficiaries
2,000
Households
10,000
Population
Technical Specs
Treatment Capacity
10,000.00 m³/day
Created 16 Aug 2026, 17:18