Ongoing
Sanitation Project
Approved
Timau Sewerage Project
Meru · Buuri · Kiirua
Overall Progress
0.00%
Project Overview
Implementing Agency
Tana Water Works Development Agency
Programme
National Urban Water Supply and Sanitataion Program (NUWSSP) Ph II
Start Date
-
Planned End
-
Actual End
-
Contractor
-
Consultant
-
Location Type
Urban
Target Areas
Timau town and its environs.
Scope of Works
▪ - Construction of 3,000m3/day wastewater stabilization ponds
-Laying of 12km lateral sewer lines (DN 250- 200mm)
- Last Mile Connectivity
- Laying of 6km DN 300mm trunk sewer line
Impacts
Provision of reliable sanitation facility
Key Challenges
Awaiting Funds allocation
Remarks
Project designed
Funding Sources
No funding sources recorded.
Total
KES 0.0M
Beneficiaries
500
Households
2,500
Population
Technical Specs
Wastewater Production Capacity
3,000.00 m³/day
Created 16 Aug 2026, 17:18