Ongoing
Sanitation Project
Approved
Construction of Biogas Production Unit at Ngaru Girls High School
- · - · -
Overall Progress
5.00%
Project Overview
Implementing Agency
Tana Water Works Development Agency
Programme
Kenya Towns Sustainable Water Supply and Sanitation Program (KTSWSSP)
Start Date
01 Oct 2024
Planned End
01 Oct 2025
Actual End
-
Contractor
Ranju Ltd
Consultant
-
Location Type
Rural
Target Areas
Ngaru Girls High School
Scope of Works
Construction of an Anaerobic Reactor
Construction of a horizontal flow constructed wetland
Construction of a treated effluent recovery pond
Impacts
Provision of reliable sanitation facilty.
Key Challenges
GOK late disbursments . Contractor citing financial constraints
Remarks
Facilitation of capacity building training for future projects .
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 9.8M
Total
KES 9.8M
Beneficiaries
1
Households
1,000
Population
Created 16 Aug 2026, 17:18