Ongoing
Borehole
Approved
Gitoo - ini Primary school
Kirinyaga · Mwea · Mutithi
Overall Progress
70.00%
Project Overview
Implementing Agency
Tana Water Works Development Agency
Programme
Cross- County Bulk Water & Sanitation Program
Start Date
-
Planned End
-
Actual End
-
Contractor
central Water Company
Consultant
-
Location Type
Rural
Target Areas
Gitoo-ini Primary School
Scope of Works
Drilling, development, test pumping and equipping
Impacts
Provision of safe water
Key Challenges
GOK late disbursments . Contractor citing financial constraints
Remarks
Need for Improved Coordination and Timely Funding
GPS Coordinates
9931736.000000000,308015.000000000
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 6.9M
Total
KES 6.9M
Beneficiaries
1
Households
1,050
Population
Created 16 Aug 2026, 17:18