Ongoing
Water Supply Project
Approved
Improvement of Water Supply for Gatumbi Dispensary
Embu · Runyenjes · Gaturi North
Overall Progress
60.00%
Project Overview
Implementing Agency
Tana Water Works Development Agency
Programme
Universal Health Coverage Program
Start Date
-
Planned End
-
Actual End
-
Contractor
Mukasi Builders
Consultant
-
Location Type
Rural
Target Areas
Gatumbi Dispensary
Scope of Works
Erection of 48m3 Pressed Steel Elevated Tank, 150m3 ground masonry tank and roof water harvesting.
Impacts
Improves access to clean water and create employment opportunities
Key Challenges
Late disbursement of government funds.
Remarks
Need for Improved Coordination and Timely Funding
GPS Coordinates
-0.377847784,37.920678650
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 5.5M
Total
KES 5.5M
Beneficiaries
1
Households
500
Population
Technical Specs
Storage Reservoir
198.00 m³
Created 16 Aug 2026, 17:18