Ongoing
Water Supply Project
Approved
Chuka Water Supply Project
Tharaka Nithi · Chuka/Igambang’ombe · Mariani, Karingani, Mugwe and Igambang,ombe
Overall Progress
96.00%
Project Overview
Implementing Agency
Tana Water Works Development Agency
Programme
Kenya Towns Sustainable Water Supply and Sanitation Program (KTSWSSP)
Start Date
02 Jan 2021
Planned End
-
Actual End
-
Contractor
Zhong Mei Engineering Group Ltd.
Consultant
Mangat IB Patel
Location Type
Urban
Target Areas
To serve Chuka town and Environs , include County HQ, Chuka University, Kanwa area and Kathwana.
Scope of Works
1.) Intake Works at Ruguti River 2.) Treatment Works 15,000 m3/day 3.) 7 Km of Raw Water and Treated water mains Ranging from 450mm-150mm 4.)15.4km transmission main 5.) 2No. Storage tanks of 500 m3 each
Impacts
• There are over 40 people employed by the project, enhancing economy of the area.
• It is expected to increase the water production for the WSP and eventually the revenue
Key Challenges
• Delay in the GOK counter fund.
• There is challenge of the way leaves.
Remarks
The works have been going on well, the TW are complete and test running is ongoing.
GPS Coordinates
-0.336375000,37.642762000
Funding Sources
Adb
🌍 Foreign
· Loan
KES 628.1M
Total
KES 628.1M
Beneficiaries
4,000
Households
20,000
Population
Technical Specs
Volume Abstracted
15,000.00 m³/day
Treatment Capacity
15,000.00 m³/day
Storage Reservoir
500.00 m³
Treated Water Mains
7.00 km
Distribution Lines
15.40 km
Connections
4,000
Created 16 Aug 2026, 17:18