Report Back to Projects
Proposed Water Supply Project Approved

Kanjuki Water Supply Project

Tharaka Nithi · Chuka/Igambang’ombe · Igambang’ombe Ward

Overall Progress
0.00%
Project Overview
Implementing Agency
Tana Water Works Development Agency
Programme
Cross- County Bulk Water & Sanitation Program
Start Date
-
Planned End
-
Actual End
-
Contractor
-
Consultant
-
Location Type
Rural
Target Areas
Kanjuki area and its envrons
Scope of Works
Laying of 10km reticulation network comprising of pipes ranging from DN 110m-63mm diameter.
Impacts
Improves access to clean water and create employment opportunities
Key Challenges
Delay for funds to implement this project
Remarks
Project at Design Stage
Funding Sources

No funding sources recorded.

Total KES 0.0M
Beneficiaries
900
Households
4,500
Population
Created 16 Aug 2026, 17:18