Proposed
Dam
Approved
Kithino Dam
Tharaka Nithi · Tharaka North · Marimanti.
Overall Progress
0.00%
Project Overview
Implementing Agency
Tana Water Works Development Agency
Programme
Public Private Partnership (PPP)
Start Date
-
Planned End
-
Actual End
-
Contractor
-
Consultant
-
Location Type
Urban
Target Areas
Mitheru and marimanti wards
Scope of Works
Develop a dam with a 44 Mm3 reservoir capacity. The project is intended to supply 54,000 m3/day of water needed for irrigating initial 8750 acres and current domestic water needs of at least 66,500
Impacts
Improves access to clean water and create employment opportunities
Key Challenges
Delay in Sourcing of the funds to implement this project
Remarks
Feasibility Study Done, waiting for the Final Designs
Funding Sources
No funding sources recorded.
Total
KES 0.0M
Beneficiaries
2,000
Households
10,000
Population
Created 16 Aug 2026, 17:18