Completed
River Intake
Approved
Tot Water Supply Project
Elgeyo-Marakwet · Marakwet East · Endo
Overall Progress
100.00%
Project Overview
Implementing Agency
North Rift Valley Water Works Developmnet Agency
Programme
Water Harvesting Program
Start Date
04 Oct 2023
Planned End
-
Actual End
04 Oct 2024
Contractor
-
Consultant
-
Location Type
Rural Urban
Scope of Works
Construction of intake weir, Raw Water Gravity Main length 4km, 1 No. Storage tank of capacity 225m3/day, Break Pressure Tanks and distribution lines.
Impacts
Project succesfully implemented
GPS Coordinates
latitude 1°12'18.26"N
longitude 35°38'17.04"E
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 60.0M
Total
KES 60.0M
Beneficiaries
1,000
Households
0
Population
Technical Specs
Storage Reservoir
200.00 m³
Created 16 Aug 2026, 17:18