Ongoing
River Intake
Approved
Cheminya Water Supply Project
Elgeyo-Marakwet · Keiyo South · Kaptarakwa
Overall Progress
90.00%
Project Overview
Implementing Agency
North Rift Valley Water Works Developmnet Agency
Programme
GOK Funded Projects
Start Date
03 Nov 2023
Planned End
09 Nov 2024
Actual End
-
Contractor
Khadim Co. Ltd
Consultant
-
Location Type
Rural
Target Areas
Kitany/Chepteran Environs.
Scope of Works
Rehabilitation of existing dam, solarization, laying of 10Km pipelines
Impacts
Increased water coverage
Improved Quality of Life
Reduction in Waterborne Diseases
Better Hygiene and Sanitation
Increased Productivity
Community Cohesion
Reforestation and Soil Conservation
Key Challenges
Issues between the project host community and the immediate neighbouring community on the source of water and extent of coverage
Remarks
Project on schedule
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 30.0M
Total
KES 30.0M
Beneficiaries
720
Households
3,600
Population
Technical Specs
Storage Reservoir
20,000.00 m³
Treated Water Mains
7.00 km
Distribution Lines
8.00 km
Water Kiosks
4