Report Back to Projects
Ongoing River Intake Approved

Kapyego Phase I

Elgeyo-Marakwet · Marakwet East · Kapyego

Overall Progress
33.00%
Project Overview
Implementing Agency
North Rift Valley Water Works Developmnet Agency
Programme
GOK Funded Projects
Start Date
10 Aug 2024
Planned End
06 Aug 2025
Actual End
-
Contractor
Ascension East Africa Ltd
Consultant
-
Location Type
Rural
Target Areas
Kapyego and Kessom sub locations of Kapyego location as well as Kararia sublocation in Kararia location Kapyego ward
Scope of Works
Construction of new intake Weir, Construction of Gravity Main 18 Km length, Construction of 4 No. Storage Tanks total capacity 525m3 and laying 22km Distribution netwok
Impacts
Increased water coverage Improved Quality of Life Reduction in Waterborne Diseases Better Hygiene and Sanitation Increased Productivity Community Cohesion Reforestation and Soil Conservation
Key Challenges
No challenge
Remarks
Project on schedule
GPS Coordinates
latitudes 1.°08'51.78" N longitudes 35° 28'42.46"
Funding Sources
Gok
🇰🇪 Domestic · Grant
KES 80.0M
Total KES 80.0M
Beneficiaries
2,178
Households
9,798
Population
Technical Specs
Volume Abstracted 600.00 m³/day
Storage Reservoir 525.00 m³
Treated Water Mains 18.00 km
Distribution Lines 22.00 km
Connections 5