Completed
Water Pan
Approved
Construction of Bilhil Burr Pan
Wajir · Wajir South · Lagbogol
Overall Progress
100.00%
Project Overview
Implementing Agency
Northern Water Works Development Agency
Programme
GOK Funded Projects
Start Date
01 May 2024
Planned End
01 Jan 2025
Actual End
01 Jan 2026
Contractor
Redmark General Supplies and Con. Ltd
Consultant
-
Location Type
-
Scope of Works
Construction of 1 no. water pan, Construction of spillway, Auxiliary works
Impacts
To Increase water storage to be used in dry periods to reduce the cost of living and inclusive growth
Key Challenges
Insufficient budgetary allocations
GPS Coordinates
569179.89 m E,
175787.85 m N
Funding Sources
No funding sources recorded.
Total
KES 0.0M
Beneficiaries
200
Households
1,200
Population
Technical Specs
Storage Reservoir
30,000.00 m³
Created 16 Aug 2026, 17:18