Rehabilitation of Andaraka Water pan

Wajir · Wajir North · Danaba

Overall Progress
100.00%
Project Overview
Implementing Agency
Northern Water Works Development Agency
Programme
GOK Funded Projects
Start Date
01 Jun 2024
Planned End
01 Feb 2025
Actual End
02 Jan 2026
Contractor
Nasbsit Holding Limited
Consultant
-
Location Type
-
Scope of Works
Construction of 1 no. water pan, Construction of spillway, Auxiliary works
Impacts
To Increase water storage to be used in dry periods to reduce the cost of living and inclusive growth
Key Challenges
Insufficient budgetary allocations
GPS Coordinates
555107.35 m E, 363347.84 m N
Funding Sources

No funding sources recorded.

Total KES 0.0M
Beneficiaries
220
Households
1,320
Population
Technical Specs
Storage Reservoir 20,400.00 m³