Completed
Water Pan
Approved
Construction of Bananey Pan
Wajir · Wajir West · Arbijahan
Overall Progress
100.00%
Project Overview
Implementing Agency
Northern Water Works Development Agency
Programme
GOK Funded Projects
Start Date
01 Aug 2024
Planned End
01 Apr 2025
Actual End
04 Jan 2026
Contractor
Al-Macruf Contractors Limited
Consultant
-
Location Type
-
Scope of Works
Construction of 1 no. water pan, Construction of spillway, Auxiliary works
Impacts
To Increase water storage to be used in dry periods to reduce the cost of living and inclusive growth
Key Challenges
Insufficient budgetary allocations
GPS Coordinates
507126.45 m E,
247596.99 m N
Funding Sources
No funding sources recorded.
Total
KES 0.0M
Beneficiaries
250
Households
1,500
Population
Technical Specs
Storage Reservoir
15,000.00 m³
Created 16 Aug 2026, 17:18