Completed
Water Pan
Approved
Construction of Ogot wein Water pan
Mandera · Mandera North · Ashabito
Overall Progress
100.00%
Project Overview
Implementing Agency
Northern Water Works Development Agency
Programme
GOK Funded Projects
Start Date
-
Planned End
01 Nov 2025
Actual End
11 Jan 2026
Contractor
Hetello Holder Limited
Consultant
-
Location Type
-
Scope of Works
Construction of 1 no. water pan, Construction of spillway, Auxiliary works
Impacts
To Increase water storage to be used in dry periods to reduce the cost of living and inclusive growth
Key Challenges
Insufficient budgetary allocations
Funding Sources
No funding sources recorded.
Total
KES 0.0M
Beneficiaries
200
Households
1,200
Population
Technical Specs
Storage Reservoir
15,000.00 m³
Created 16 Aug 2026, 17:18