Report Back to Projects
Proposed Water Supply Approved

Kiambaa water supply

Kiambu · Kiambaa · Karuri, Cianda, Ndenderu, Muchatha, Kihara wards

Overall Progress
0.00%
Project Overview
Implementing Agency
Athi Water Works Development Agency
Programme
GOK Funded Projects
Start Date
-
Planned End
-
Actual End
-
Contractor
Invegus Limited
Consultant
-
Location Type
Urban
Target Areas
Karuri, Cianda, Ndenderu, Muchatha, Kihara wards
Scope of Works
Construction of 2m high intake weir along the Riara River. Laying of a 450m HDPE raw water pipelines. Construction of Water Treatment Plant comprising of; Stilling Well and Dosing Chmaber and 1 no. 750m3 composite Filtration Unit. Laying of 3.5km of DN 160 HDPE trated water pipeline.
GPS Coordinates
-1.1764, 36.7564
Funding Sources

No funding sources recorded.

Total KES 0.0M
Beneficiaries
80,232
Households
236,400
Population
Created 16 Aug 2026, 17:18
County Overview
Loading…
Loading…

Fetching entity performance details…